McGeorge is excited to get back to work in South Arkansas

In July 2020, McGeorge began a project to widen 1.79 miles of Highway 167 in Calhoun County. This project consists of clearing and grubbing, removal and disposal items, earthwork, aggregate base course, asphalt base, binder, and surface courses, cold milling asphalt pavement, asphalt patching and existing roadway, maintenance of traffic, minor drainage structures, erosion control items, traffic signal items, pavement markings and misc. items.

  • Bid Amount $12.5 Mil
  • Days to Complete: 1100
  • Appx. Completion Date: August, 2023
  • County: Calhoun
  • Highway: Hwy 79 South through Hampton 1.769 miles

HWY 67 South small


In August 2020, McGeorge started widening work on Highway 167 in Calhoun Co., Arkansas. The purpose of this project is to widen Highway 167 and replace a bridge structure with a reinforced box culvert in Calhoun County. This project consists of clearing and grubbing, removal and disposal items, earthwork, Asphalt base, binder, and surface courses, cold milling, Asphalt patching of existing roadway, approach slabs and gutters, maintenance of traffic, minor drainage, guardrail, erosion control items, rumble strips, one triple R.C. box culvert, one continuous composite w-beam unit bridge, polyester polymer concrete overlay and deck repair on one bridge, pavement marking and misc. items.

  • Bid Amount $27.9 Mil
  • Days to Complete: 700
  • Appx. Completion Date: July 5, 2022
  • County: Calhoun
  • Highway: Hwy 79 South (widening) 5.682 Miles
  • Project Begin Location: Hwy 79 ramp to Hwy 167 S
  • Project End Location: Calhoun Co Rd 64

HWY 67 South small 27

 

Contact Us

Questions? Fill out this brief form and one of our team members will respond promptly.

contact

Join Our Team

We offer competitive pay and benefits with long-term stability and advancement opportunities.

see jobs